CONSTRUCTION UPDATES
June / July Construction Update

During the months of June and July 70% of the concrete mat slab was poured. The columns and foundation walls were poured on the finished portions of the mat slab. All steel rebar was delivered on site in preparation for the cast-in-place 1st floor deck pour. The remaining decks up to the 7th floor will be constructed using a pre-cast plank structure.

Major construction activities have begun at the Terrazio! The existing buildings originally on site were demolished to make way for the large scale courtyard style development. Earth retention work is near completion and excavation is ongoing. The excavator is continuing to remove massive amounts of soil across the site to a depth of approximately 14 ft below grade. Construction on the foundation has begun on the excavated south 1/3 portion of the land along Cullerton and Wabash Streets. Steel rebar is being put down in preparation for three major concrete pours to form the thick mat slab which will support the building superstructure.

>